Welcome
Welcome! |
The Mid-Dakota Rural Water System... serves over 5,200 customers including 28 town or community water systems. Mid-Dakota includes approximately 3,800 miles of pipeline with users residing in 14 counties in the east-central portion of South Dakota. Currently Mid-Dakota has completed its final stages of construction on the originally authorized project. However, it is expected that the Mid-Dakota Rural Water System will continue to grow through expansion projects as well as the addition of Add-On Users. |
Upcoming Events
|
Send meter readings to: reading@mdrws.com Mid-Dakota Activities |
|
|---|---|
|
Cavour Meeting Annual Meeting
October 12, 2012 - 8:00 am - 6:00 pm, all Mid-Dakota offices. Board Meetings June 12, 2012 - 4:30 pm, Miller Operations & Maintenance Center - Board Room |
Construction Activities Contract 4-6 Schedule 1 - Eatherly Constructors, Inc. Work is currently progressing thanks to the favorable weather we are experiencing. Eatherly will continue to install services as long as the good weather continues. The contract is scheduled for substantial completion by September of 2012. Contract 4-6 Schedule 2 - Carstensen Contracting, Inc. Carstensen has begun work to construct a pipeline that will serve users within the exterior boundaries of the Crow Creek Reservation. Substantial completion of this contract is scheduled for August of 2012.
|
